Description
36” Mainline Natural Gas Transmission Pipeline :
- From LNG Terminal in Port Sudan to Kosti via Atbara and Khartoum.
- 1046 km long.
- 29 Intermediate Block Valve Stations at Approx. 36 km Spacings.
- Up to 4 Future Phase Compressor Stations.
Mainline Offtake Stations:
- Port Sudan
- Haiya (Future)
- Atbara
- Garri
- Khartoum North
- Elbagair
- Rabak Offtake Distribution Pipelines From Mainline Transmission Pipeline to Individual Consumers (Power Stations and Cement factories)